Power & Energy
Energy Commission site visit
A site visit with the Energy Commission to assess the project site and verify compliance with the applicable standards and regulatory requirements for approval.

At a glance
Client
Ghana Thermal Power Limited (GTPL)
Sector
Power & Energy
Location
Kafodzidzi–Abrobiano, KEEA, Central Region
Year
July 2026
Our role
Project management consultancy
01
The challenge
Ghana Thermal Power Limited (GTPL) is developing a 1,200 MW gas-fired thermal power plant at Kafodzidzi–Abrobiano in the KEEA Municipality. Before it can proceed, the Energy Commission reviews GTPL's siting-permit application.
02
Our approach
As project management consultant across the plant's full lifecycle, Vertex Ridge took part in the Energy Commission's site visit in July 2026, as the Commission assessed the site and verified compliance with the applicable standards and regulatory requirements.
03
The outcome
The first phase of 600 MW is targeted for commissioning in 2028.